Multiple Choice
When a work package is returned, which of the following actions does PRINCE2 recommend?
1) Notify the Project Board
2) Update the Team Plan
3) Review the Approval Records
4) Update the Stage Plan
A) 1 and 2
B) 2 and 3
C) 1, 2, and 3
D) 1, 3, and 4
Correct Answer:

Verified
Correct Answer:
Verified