Multiple Choice
James Kirk is the project manager for a 5-year project, with a time tolerance of +3 months for the current stage. One of his team leaders, Monty Scott, reports a projected problem with a work package that is expected to take an extra 2 weeks. What action should Kirk take?
A) None
B) Produce an Exception Report.
C) Cancel the project.
D) Add an entry to the Risk Register.
Correct Answer:

Verified
Correct Answer:
Verified