Question 81
Multiple Choice
What name is given to the piece of work performed by a Team Manager for the Project Manager?
Question 82
Multiple Choice
Which role is responsible for defining the role descriptions within the project?
Question 83
Multiple Choice
Which PRINCE2 theme addresses the ongoing viability of the different project plans?
Question 84
Multiple Choice
Which process can be carried out without using PRINCE2?
Question 85
Multiple Choice
What are the two types of progress controls provided by PRINCE2? 1) Stage-driven 2) Tolerance-driven 3) Time-driven 4) Event-driven
Question 86
Multiple Choice
Which of the following statements is true about a PRINCE2 project?
Question 87
Multiple Choice
Which of the following products is NOT related to the PRINCE2 approach to change?
Question 88
Multiple Choice
Which role has the responsibility of setting project tolerances?
Question 89
Multiple Choice
When a work package is returned, which of the following actions does PRINCE2 recommend? 1) Notify the Project Board 2) Update the Team Plan 3) Review the Approval Records 4) Update the Stage Plan
Question 90
Multiple Choice
James Kirk is the project manager for a 5-year project, with a time tolerance of +3 months for the current stage. One of his team leaders, Monty Scott, reports a projected problem with a work package that is expected to take an extra 2 weeks. What action should Kirk take?
Question 91
Multiple Choice
Which of the following is NOT a PRINCE2 theme?
Question 92
Multiple Choice
Which role(s) has/have ultimate authority on the Project Board?
Question 93
Multiple Choice
Which role is responsible for defining and verifying user requirements and expectations?
Question 94
Multiple Choice
Which of the following supports the PRINCE2 principle of Management by Exception?
Question 95
Multiple Choice
Which 3 products are created once the authority to initiate the project has been received?
Question 96
Multiple Choice
Which of the following is NOT a type of Issue?
Question 97
Multiple Choice
Which document is used to record issues and risks in the Starting up a Project process if the appropriate registers have not yet been created?
Question 98
Multiple Choice
If there is more than one version of a document in circulation, what action should the Project Manager take?
Question 99
Multiple Choice
Which role confirms stage and project progress against agreed tolerances?