Multiple Choice
Which of the following supports the PRINCE2 principle of Management by Exception?
A) Delegation of authority.
B) Creating the Product Flow Diagram.
C) Maintaining the Business Case.
D) Creating a Request for Change.
Correct Answer:

Verified
Correct Answer:
Verified