menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Trade & Technology
  3. Study Set
    Estimating and Costing
  4. Exam
    Exam 2: Mecasurement and Estimation in Construction Work
  5. Question
    Due to Change in Price Level, a Revised Estimate Is
Solved

Due to Change in Price Level, a Revised Estimate Is

Question 16

Question 16

Multiple Choice

Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds


A) 2.0 %
B) 2.5 %
C) 4.0 %
D) 5.0 %

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q11: Pick up the correct statement from the

Q12: In long and short wall method of

Q13: The concrete work for the following part

Q14: While preparing a detailed estimate<br>A)dimension should be

Q15: According to ISI method of measurement, the

Q17: The expected out turn of 2.5 cm

Q18: The value of 'A' of Indian type

Q19: The cost of the earthwork in excavation

Q20: The most reliable estimate is<br>A)detailed estimate<br>B)preliminary estimate<br>C)plinth

Q21: The value of 'C' of Indian type

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines