Question 17

Question 17

Multiple Choice

The expected out turn of 2.5 cm cement concrete floor per mansion per day


A) 2.5 sqm
B) 5.0 sqm
C) 7.5 sqm
D) 10 sqm

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q12: In long and short wall method of

Q13: The concrete work for the following part

Q14: While preparing a detailed estimate<br>A)dimension should be

Q15: According to ISI method of measurement, the

Q16: Due to change in price level, a

Q18: The value of 'A' of Indian type

Q19: The cost of the earthwork in excavation

Q20: The most reliable estimate is<br>A)detailed estimate<br>B)preliminary estimate<br>C)plinth

Q21: The value of 'C' of Indian type

Q22: Pick up the correct statement from the

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines