Solved

The Table Provides a Project with the Task Lengths (In

Question 30

Multiple Choice

The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.
The table provides a project with the task lengths (in days)  and precedence requirements, as well as the three time estimates.    -Calculate the variance of the project's expected completion time. A) 0.054 B) 0.174 C) 0.399 D) 0.117 E) 0.340
-Calculate the variance of the project's expected completion time.


A) 0.054
B) 0.174
C) 0.399
D) 0.117
E) 0.340

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions