Multiple Choice
The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.
-Calculate the variance of the project's expected completion time.
A) 0.054
B) 0.174
C) 0.399
D) 0.117
E) 0.340
Correct Answer:

Verified
Correct Answer:
Verified