Multiple Choice
The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.
-Calculate completion time variance for Task B.
A) 0.054
B) 0.174
C) 0.399
D) 0.117
E) 0.340
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q22: The table provides a project with the
Q23: Ivy Inc. has planned a simple project
Q24: The table provides a project with the
Q25: The table below shows the tasks required
Q26: The table provides a project with the
Q28: A procurement specialist wished to assess the
Q29: The table provides a project with the
Q30: The table provides a project with the
Q31: The table provides a project with the
Q32: The table provides a project with the