Multiple Choice
The table provides a project with the task lengths (in days) and precedence requirements.
-Based on the information, which of the following statements is true?
A) None of the paths in the project is a critical path.
B) Path ACD is the critical path for the project.
C) Path ABD is the critical path for the project.
D) Path ABCD is a valid path for the project.
E) Tasks A, B, C, and D lie in the critical path for the project.
Correct Answer:

Verified
Correct Answer:
Verified