Question 10

Multiple Choice

The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.
The table provides a project with the task lengths (in days)  and precedence requirements, as well as the three time estimates.    -What are the expected days to completion? A) 20.98 B) 25.93 C) 22.09 D) 31.98 E) 26.00
-What are the expected days to completion?


A) 20.98
B) 25.93
C) 22.09
D) 31.98
E) 26.00