Multiple Choice
The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.
-What are the expected days to completion?
A) 20.98
B) 25.93
C) 22.09
D) 31.98
E) 26.00
Correct Answer:

Verified
Correct Answer:
Verified