Multiple Choice
The table provides a project with the task lengths (in days) and precedence requirements.
-Calculate the late start (LS) time for Task C.
A) 23 days
B) 15 days
C) 30 days
D) 18 days
E) 20 days
Correct Answer:

Verified
Correct Answer:
Verified