Solved

The Table Provides a Project with the Task Lengths (In

Question 9

Multiple Choice

The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.
The table provides a project with the task lengths (in days)  and precedence requirements, as well as the three time estimates.    -Based on the information, what are the days to completion? A) 21 days B) 22 days C) 26 days D) 32 days E) Need more information to answer the question
-Based on the information, what are the days to completion?


A) 21 days
B) 22 days
C) 26 days
D) 32 days
E) Need more information to answer the question