Multiple Choice
A project is composed of 6 tasks that have durations and precedence requirements shown in the table. How long should we expect it to take to complete this project?
A) 25
B) 21
C) 29
D) 19
E) 36
Correct Answer:

Verified
Correct Answer:
Verified