The Table Provides a Project with the Task Lengths (In

Question 32

Multiple Choice

The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.
The table provides a project with the task lengths (in days)  and precedence requirements, as well as the three time estimates.    -Based on the information, which of the following statements is true? A) None of the paths in the project is a critical path. B) Path ABEF is the critical path for the project. C) Path ABDF is the critical path for the project. D) Path ACDF is the critical path for the project. E) Tasks A, B, C, D, and F lie in the critical path for the project.
-Based on the information, which of the following statements is true?


A) None of the paths in the project is a critical path.
B) Path ABEF is the critical path for the project.
C) Path ABDF is the critical path for the project.
D) Path ACDF is the critical path for the project.
E) Tasks A, B, C, D, and F lie in the critical path for the project.