Multiple Choice
Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project.
-Calculate the early finish (EF) time for Task T.
A) 6 weeks
B) 17 weeks
C) 12 weeks
D) 23 weeks
E) 18 weeks
Correct Answer:

Verified
Correct Answer:
Verified