Question 37

Multiple Choice

The table provides a project with the task lengths (in days) and precedence requirements, as well as the associated task costs, crashed time, and crash costs.
The table provides a project with the task lengths (in days)  and precedence requirements, as well as the associated task costs, crashed time, and crash costs.    -Which statement out of the following is NOT correct? A) The crash cost per day for Task A is greater than the crash cost per day for Task C. B) The crash cost per day for Task E is 200 dollars less than the crash cost per day for Task D. C) The crash cost per day for Task B is $750. D) The crash cost per day for Task C is more than the crash cost per day for Task F. E) The total normal cost of the project is $3,650.
-Which statement out of the following is NOT correct?


A) The crash cost per day for Task A is greater than the crash cost per day for Task C.
B) The crash cost per day for Task E is 200 dollars less than the crash cost per day for Task D.
C) The crash cost per day for Task B is $750.
D) The crash cost per day for Task C is more than the crash cost per day for Task F.
E) The total normal cost of the project is $3,650.