Question 33

Multiple Choice

A lean system uses 12 containers, each of which can hold 12 parts. The lead time required to round-trip one container through the system is normally 3 hours. The usual safety stock is 20%.
-What is the maximum demand rate this system can accommodate?


A) 10 parts per hour
B) 20 parts per hour
C) 30 parts per hour
D) 40 parts per hour
E) 50 parts per hour

Correct Answer: