Multiple Choice
Copenhagen Industries uses a kanban system to manage production of their subassembly. In a 10-hour day, they use 1,500 units and use containers that can hold 50 units each. It takes 45 minutes to fill and move a container of parts to the right place on the subassembly line that is currently rated at a 15% safety factor.
-Calculate the maximum system inventory for this part.
A) 4,100 units
B) 400 units
C) 150 units
D) 5,000 units
E) 1,300 units
Correct Answer:

Verified
Correct Answer:
Verified
Q23: Berlin Industries uses a kanban system to
Q24: Lady Bug Machineries uses a lean production
Q25: Istanbul Industries uses a kanban system to
Q26: Lady Bug Machineries uses a lean production
Q27: The Frankenmuth Fasteners Co. was implementing lean
Q29: An integrated electronic-chip manufacturer has a demand
Q30: A lean system has the following characteristics:
Q31: The Frankenmuth Fasteners Co. was implementing lean
Q32: Copenhagen Industries uses a kanban system to
Q33: A lean system uses 12 containers, each