Multiple Choice
A lean system uses 12 containers, each of which can hold 12 parts. The lead time required to round-trip one container through the system is normally 3 hours. The usual safety stock is 20%.
-If the demand rate is changed to 50 parts per hour, what would be the new container size, all else being constant?
A) 12 parts
B) 15 parts
C) 10 parts
D) 20 parts
E) Need additional information to compute the value
Correct Answer: