Multiple Choice
Lady Bug Machineries uses a lean production assembly line to make its generators. In one assembly area, the demand is 200 parts per 8-hour day. It uses a container that holds 10 parts. It typically takes about 5 hours to round-trip a container from one work center to the next and back again. They also desire to hold a 20% safety stock of this part in the system.
-If the container size from the original data was changed to 15, and there were 10 containers in the system, what is the maximum inventory for this part?
A) 250 units
B) 100 units
C) 150 units
D) 130 units
E) 200 units
Correct Answer:

Verified
Correct Answer:
Verified
Q14: Copenhagen Industries uses a kanban system to
Q15: The Frankenmuth Fasteners Co. was implementing lean
Q16: Istanbul Industries uses a kanban system to
Q17: Istanbul Industries uses a kanban system to
Q18: Lady Bug Machineries uses a lean production
Q20: Berlin Industries uses a kanban system to
Q21: A lean system uses 12 containers, each
Q22: A lean system uses 12 containers, each
Q23: Berlin Industries uses a kanban system to
Q24: Lady Bug Machineries uses a lean production