Lady Bug Machineries uses a lean production assembly line to make its generators. In one assembly area, the demand is 200 parts per 8-hour day. It uses a container that holds 10 parts. It typically takes about 5 hours to round-trip a container from one work center to the next and back again. They also desire to hold a 20% safety stock of this part in the system.
-Based on the required safety stock of zero and the number of containers computed in Question 33, what would be the new required round-trip time, all else being constant?
A) 4.4 hours
B) 5.2 hours
C) 6.6 hours
D) 7.8 hours
E) 8 hours
Correct Answer:

Verified
Correct Answer:
Verified
Q21: A lean system uses 12 containers, each
Q22: A lean system uses 12 containers, each
Q23: Berlin Industries uses a kanban system to
Q24: Lady Bug Machineries uses a lean production
Q25: Istanbul Industries uses a kanban system to
Q27: The Frankenmuth Fasteners Co. was implementing lean
Q28: Copenhagen Industries uses a kanban system to
Q29: An integrated electronic-chip manufacturer has a demand
Q30: A lean system has the following characteristics:
Q31: The Frankenmuth Fasteners Co. was implementing lean