Lady Bug Machineries Uses a Lean Production Assembly Line to Make

Question 24

Multiple Choice

Lady Bug Machineries uses a lean production assembly line to make its generators. In one assembly area, the demand is 200 parts per 8-hour day. It uses a container that holds 10 parts. It typically takes about 5 hours to round-trip a container from one work center to the next and back again. They also desire to hold a 20% safety stock of this part in the system.
-Based on the required safety stock of zero and the number of containers computed in Question 33, what will be the demand for an 8-hour day, all else being constant?


A) 240 parts
B) 26 parts
C) 208 parts
D) 30 parts
E) 200 parts

Correct Answer: