For the Buehler Bakery, the desired output for a 8 hour workday is 450 units. The discrete tasks required to produce the product have been identified, timed in seconds, and ordered as indicated in the table.
-Assuming 1 work center per task, what is the maximum output per day?
A) 360 units per day
B) 450 units per day
C) 480 units per day
D) 1920 units per day
E) Need more information to answer the question