Multiple Choice
For the Buehler Bakery, the desired output for a 8 hour workday is 450 units. The discrete tasks required to produce the product have been identified, timed in seconds, and ordered as indicated in the table.
-Assuming 1 work center per task, what is the minimum takt time?
A) 15 seconds
B) 80 seconds
C) 60 seconds
D) 64 seconds
E) Need more information to answer the question