Multiple Choice
Consider the following work breakdown structure:
What is the estimated standard deviation in the time for activity E?
A) 2 days
B) 3 days
C) 4 days
D) 16 days
E) 24 days
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q2: A project is represented by the following
Q4: Consider the following work breakdown structure: <img
Q5: Consider the following work breakdown structure: <img
Q8: Consider the following work breakdown structure: <img
Q9: Consider the following work breakdown structure: <img
Q10: In order to determine the probability of
Q11: A method used for establishing a logical
Q12: Consider the following work breakdown structure: <img
Q54: If an activity is determined to be
Q71: The earliest finish time for an activity