Multiple Choice
Consider the following work breakdown structure:
What is the probability that the critical path for this project will be completed within 200 days?
A) 0.8413
B) 0.9544
C) 0.9772
D) 0.9974
E) 0.9987
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q4: Consider the following work breakdown structure: <img
Q5: Consider the following work breakdown structure: <img
Q7: Consider the following work breakdown structure: <img
Q9: Consider the following work breakdown structure: <img
Q10: In order to determine the probability of
Q11: A method used for establishing a logical
Q12: Consider the following work breakdown structure: <img
Q54: If an activity is determined to be
Q71: The earliest finish time for an activity
Q101: The standard deviation of the critical path