Multiple Choice
Consider the following work breakdown structure:
What is the estimated expected (mean) time for activity Y?
A) 30 days
B) 29 days
C) 38 days
D) 26 days
E) 35 days
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q4: Consider the following work breakdown structure: <img
Q5: Consider the following work breakdown structure: <img
Q7: Consider the following work breakdown structure: <img
Q8: Consider the following work breakdown structure: <img
Q10: In order to determine the probability of
Q11: A method used for establishing a logical
Q12: Consider the following work breakdown structure: <img
Q14: Consider the following work breakdown structure: <img
Q71: The earliest finish time for an activity
Q101: The standard deviation of the critical path