Multiple Choice
Consider the following work breakdown structure:
What is the estimated slack time for activity E?
A) 0 weeks
B) 3 weeks
C) 9 weeks
D) 11 weeks
E) 12 weeks
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q2: A project is represented by the following
Q4: Consider the following work breakdown structure: <img
Q7: Consider the following work breakdown structure: <img
Q8: Consider the following work breakdown structure: <img
Q9: Consider the following work breakdown structure: <img
Q10: In order to determine the probability of
Q11: A method used for establishing a logical
Q54: If an activity is determined to be
Q71: The earliest finish time for an activity
Q79: The costs associated with risk events tend