Multiple Choice
A drawback of Gantt charts is ______.
A) they may not show the exact sequencing of one activity to another
B) they are complex to develop
C) they are time-consuming to develop
D) they are expensive to develop
Correct Answer:

Verified
Correct Answer:
Verified