Multiple Choice
A merge point refers to ______.
A) a node along the critical path
B) a node with two or more immediate predecessors
C) a node with two or more immediate and successive nodes
D) a node that represents the point where cross-functional resources are pooled
Correct Answer:

Verified
Correct Answer:
Verified
Q54: To complete a project quickly,we should _.<br>A)crash
Q55: Scope creep is _.<br>A)a rare occurrence in
Q56: The late finish time (LF)is _.<br>A)the latest
Q57: Which of the following correctly pairs the
Q58: A drawback of Gantt charts is _.<br>A)they
Q60: A critical path _.<br>A)is the longest individual
Q61: The backward pass _.<br>A)starts at the end
Q62: The term greenwashing refers to _.<br>A)a superficial
Q63: In the AOA method,_.<br>A)an arrow represents an
Q64: Which of the following statements is true