Solved

The Late Finish Time (LF)is ______

Question 56

Multiple Choice

The late finish time (LF) is ______.


A) the latest possible date an activity can be completed without delaying the project's completion
B) the maximum extent to which an activity can be delayed
C) the latest possible date an activity can be completed before the activity becomes irrelevant
D) the latest possible time an activity can be completed on a given day