If the standard deviation is 2.78 and the Z value is 1.65,then ______.
A) the expected date of completion is 34.59 weeks if the due date for project completion is 30 weeks
B) the due date for project completion is 34.59 weeks if the expected date of completion is 30 weeks
C) the due date for project completion is 30 weeks if the expected date of completion is 24.51weeks
D) the due date for project completion is 24.51 weeks if the expected date of completion is 30 weeks