Multiple Choice
If the most optimistic and pessimistic times for a task are 6 and 21 days respectively,then the variance for the duration of the activity is ______.
A) 5.25
B) 6.25
C) 7.25
D) 8.25
Correct Answer:

Verified
Correct Answer:
Verified