Multiple Choice
If the most optimistic time for completing an activity is 6,the most likely time is 9,and the most pessimistic time is 14,then the estimated time for the activity is ______.
A) 9.33
B) 11.63
C) 12.38
D) 9.54
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q80: If the most optimistic time for completing
Q81: Find the area under the normal curve
Q82: The variance for a project's duration is
Q83: If the most optimistic and pessimistic times
Q84: If the standard deviation is 2.78 and
Q86: When we consider crashing a project,we need
Q87: If the most optimistic time for completing
Q88: An Activity X has a duration of
Q89: In calculating the probability of a project
Q90: Find the area under the normal curve