Multiple Choice
An Activity X has a duration of 5 weeks and is budgeted to cost $12,000.The crash time for this activity is 3 weeks and is expected to cost $32,000.The cost slope for Activity X is given by ______.
A) (32,000 - 12,000) divided by (5 - 3)
B) (5 - 3) divided by (32,000 - 12,000)
C) 32,000 divided by 5
D) 12,000 divided by 3
Correct Answer:

Verified
Correct Answer:
Verified