Multiple Choice
Which of the following correctly pairs the terminology used in the earned value management (EVM) method with its description?
A) schedule performance index: the earned value to date divided by the planned value of work scheduled to be performed (EV/PV)
B) cost performance index: the earned value divided by the planned cumulative cost of the work performed to date (EV/AC)
C) both A and B are correct
D) neither A nor B is correct
Correct Answer:

Verified
Correct Answer:
Verified