    If the Standard Deviation Is 6
Solved

If the Standard Deviation Is 6

Question 42

Question 42

Multiple Choice

If the standard deviation is 6.2,the Z value is 2.00,and the expected date of completion is 33 months,then the due date for project completion is ______.


A) 45.40 months
B) 35.75 months
C) 29.65 months
D) 39.55 months

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q37: In project management,PERT (program evaluation and review

Q38: Find the area under the normal curve

Q39: Which of the following correctly pairs the

Q40: If the most optimistic time for completing

Q41: Which of the following statements is true

Q43: Find the area under the normal curve

Q44: In considering crashing activities,we first want to

Q45: A project's variance is _.<br>A)the sum of

Q46: A project's standard deviation is _.<br>A)the square

Q47: We may need to consider noncritical activities

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines