Multiple Choice
If the standard deviation is 6.2,the Z value is 2.00,and the expected date of completion is 33 months,then the due date for project completion is ______.
A) 45.40 months
B) 35.75 months
C) 29.65 months
D) 39.55 months
Correct Answer:

Verified
Correct Answer:
Verified