Multiple Choice
In project management,PERT (program evaluation and review technique) ______.
A) uses a weighted average of optimistic,pessimistic,and most likely estimates to calculate the expected duration for an activity
B) uses a deterministic approach to calculate the expected duration for an activity
C) use a simple average of optimistic,pessimistic,and most likely estimate to calculate the expected duration for an activity
D) uses a most likely estimate to calculate the expected duration for an activity
Correct Answer:

Verified
Correct Answer:
Verified
Q32: If an activity cannot be shortened,then _.<br>A)the
Q33: The normal activity duration of Activity X
Q34: Which of the following statements is true
Q35: Find the area under the normal curve
Q36: In the formula for the expected duration
Q38: Find the area under the normal curve
Q39: Which of the following correctly pairs the
Q40: If the most optimistic time for completing
Q41: Which of the following statements is true
Q42: If the standard deviation is 6.2,the Z