In Project Management,PERT (Program Evaluation and Review Technique)______

Question 37

Multiple Choice

In project management,PERT (program evaluation and review technique) ______.


A) uses a weighted average of optimistic,pessimistic,and most likely estimates to calculate the expected duration for an activity
B) uses a deterministic approach to calculate the expected duration for an activity
C) use a simple average of optimistic,pessimistic,and most likely estimate to calculate the expected duration for an activity
D) uses a most likely estimate to calculate the expected duration for an activity