menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Operations Management Managing
  4. Exam
    Exam 4: Supplement: Project Management
  5. Question
    If the Most Optimistic Time for Completing an Activity Is
Solved

If the Most Optimistic Time for Completing an Activity Is

Question 40

Question 40

Multiple Choice

If the most optimistic time for completing an activity is 3,the most likely time is 4,and the most pessimistic time is 11,then the estimated time for the activity is ______.


A) 5
B) 4
C) 6
D) 9

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q35: Find the area under the normal curve

Q36: In the formula for the expected duration

Q37: In project management,PERT (program evaluation and review

Q38: Find the area under the normal curve

Q39: Which of the following correctly pairs the

Q41: Which of the following statements is true

Q42: If the standard deviation is 6.2,the Z

Q43: Find the area under the normal curve

Q44: In considering crashing activities,we first want to

Q45: A project's variance is _.<br>A)the sum of

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines