Multiple Choice
If a project has an expected completion time of 15 weeks with a variance of 4 weeks,there is a 95% likelihood that the project will be completed by what time?
A) by 17.5 weeks
B) by 16.5 weeks
C) by 15.5 weeks
D) by 14.5 weeks