If the standard deviation is 2.7,the Z value is 1.65,and the expected date of completion is 27 weeks,then the due date for project completion is ______.
A) 31.46 weeks
B) 22.55 weeks
C) 32.35 weeks
D) 46.45 weeks
Correct Answer:

Verified
Correct Answer:
Verified