Multiple Choice
If the standard deviation is 1.9,the Z value is 1.65,and the expected date of completion is 25 months,then the due date for project completion is ______.
A) 28.135 months
B) 26.665 months
C) 32.455 months
D) 18.155 months
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q90: Find the area under the normal curve
Q91: Find the area under the normal curve
Q92: Which one of the following is a
Q93: If the most optimistic time for completing
Q94: The work breakdown structure _.<br>A)identifies the individual
Q95: If a project is expected to be
Q96: If the standard deviation is 2.7,the Z
Q97: If a project has an expected completion
Q98: If the most optimistic time for completing
Q100: Let us say that x is an