Multiple Choice
If the most optimistic time for completing an activity is 3,the most likely time is 5,and the most pessimistic time is 12,then the estimated time for the activity is ______.
A) 5.83
B) 6.42
C) 10.58
D) 9.11
Correct Answer:

Verified
Correct Answer:
Verified