    When Developing a Project Schedule,total Float Refers to the Amount
Solved

When Developing a Project Schedule,total Float Refers to the Amount

Question 51

Question 51

True/False

When developing a project schedule,total float refers to the amount of time a schedule activity may be delayed from its early start date without delaying the project end date.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q46: Even small delays on "near-critical" activities can

Q47: A successor activity is the schedule activity

Q48: The length of time to perform an

Q49: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 7-6 Network

Q50: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 7-3 System

Q52: Creating a realistic schedule is often an

Q53: Which of the following responses identifies a

Q54: While the lowest level of decomposition in

Q55: Faced with significant schedule challenges,the project manager

Q56: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 7-4 Lab

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines