Figure 7-3 System Integration Project

Question 50

Multiple Choice

  Figure 7-3 System Integration Project -Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,how many days can you delay the purchase of software (Activity C) ,without impacting the expected project completion date?  A)  0 days  B)  1 day  C)  2 days  D)  4 days Figure 7-3 System Integration Project
-Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,how many days can you delay the purchase of software (Activity C) ,without impacting the expected project completion date? 


A)  0 days 
B)  1 day 
C)  2 days 
D)  4 days