Faced with significant schedule challenges,the project manager has an ethical responsibility to do all of the following EXCEPT:
A) willingly accept end dates dictated by customers or sponsors
B) persuade all stakeholders that the schedule makes sense
C) deliver the project according to the agreed-upon schedule
D) determine a schedule that is possible to achieve
Correct Answer:

Verified
Correct Answer:
Verified
Q46: Even small delays on "near-critical" activities can
Q47: A successor activity is the schedule activity
Q48: The length of time to perform an
Q49: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 7-6 Network
Q50: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 7-3 System
Q51: When developing a project schedule,total float refers
Q52: Creating a realistic schedule is often an
Q53: Which of the following responses identifies a
Q54: While the lowest level of decomposition in
Q56: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 7-4 Lab