Multiple Choice
If the crash cost is $2,500,the normal cost is $1,500,the crash time is 4,and the normal time is 6,what is the slope?
A) -1,500
B) -1,000
C) -750
D) -500
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q7: If a predecessor activity finishes early,will the
Q8: Match the following priority rules with their
Q9: The _ heuristic provides a general solution
Q10: If the crash cost is $2,500,the normal
Q11: In some situations,two activities are scheduled to
Q13: A project task is said to be
Q14: Because the project _ is the source
Q15: Assume two activities,printing and binding.Printing is a
Q16: Match the following priority rules with their
Q17: With respect to project scheduling,_ is the