Match the following priority rules with their descriptions.
A)Minimum Slack First
B)Most Critical Followers
C)Most Successors
D)Arbitrary
1)This heuristic orders activities by the amount of slack,least slack going first.
2)Tasks are arranged by number of activities following them.
3)Priorities are assigned to activities according to some rule not associated with task length,slack,or resource requirements.
4)Tasks are arranged by number of critical activities following them.
Correct Answer:

Verified
Correct Answer:
Verified
Q3: Suggest some options for leveling the load
Q4: Match the following priority rules with additional
Q5: The principal reason why a project manager
Q6: List some of the common priority rules
Q7: If a predecessor activity finishes early,will the
Q9: The _ heuristic provides a general solution
Q10: If the crash cost is $2,500,the normal
Q11: In some situations,two activities are scheduled to
Q12: If the crash cost is $2,500,the normal
Q13: A project task is said to be