Multiple Choice
If the crash cost is $2,500,the normal cost is $2,000,the crash time is 1,and the normal time is 6,what is the slope?
A) -300
B) -200
C) -100
D) None of the above are correct
Correct Answer:

Verified
Correct Answer:
Verified