Multiple Choice
In earned value analysis,the __________ is computed as the earned value minus the actual cost of work performed.
A) schedule variance
B) cost variance
C) time variance
D) CPI
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q9: For project management,there are three distinct types
Q10: There are several conventions used to aid
Q11: In earned value Analysis,the 0 - 100
Q12: What is the relationship between management level
Q13: There are several conventions used to aid
Q15: Alderton suggests telltale signs of project trouble.Match
Q16: List the four conventions used to aid
Q17: Which of the following is not a
Q18: If EV = $500,AC = $475,PV =
Q19: ETC + AC = _.<br>A)BAC<br>B)EAC<br>C)SPI<br>D)CPI