menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management Study Set 1
  4. Exam
    Exam 10: Monitoring and Information Systems
  5. Question
    In Earned Value Analysis,the __________ Is Computed as the Earned
Solved

In Earned Value Analysis,the __________ Is Computed as the Earned

Question 14

Question 14

Multiple Choice

In earned value analysis,the __________ is computed as the earned value minus the actual cost of work performed.


A) schedule variance
B) cost variance
C) time variance
D) CPI

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q9: For project management,there are three distinct types

Q10: There are several conventions used to aid

Q11: In earned value Analysis,the 0 - 100

Q12: What is the relationship between management level

Q13: There are several conventions used to aid

Q15: Alderton suggests telltale signs of project trouble.Match

Q16: List the four conventions used to aid

Q17: Which of the following is not a

Q18: If EV = $500,AC = $475,PV =

Q19: ETC + AC = _.<br>A)BAC<br>B)EAC<br>C)SPI<br>D)CPI

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines